Case Study

Education

Energy Demonstrator, Thornton Science Park

Chester

Client
University of Chester
Location
Chester
Value
£3.85M
Contractor
Willmott Dixon
Start
June 2016
Completion
March 2017
Sector
Education
Form of Contract
JCT 2011
Delivery Type
Design & Build

Design and refurbishment of 3,131m2 existing building shell to accommodate workshop, lab and office space to ground and first floor areas, including façade and roof upgrades.

A ground-breaking energy demonstrator; this testing facility with microgrid renewable energies is a first for this client and the first time a project has been delivered for them through NWCH.

PowerHouse Energy Group has already entered into a Heads of Terms agreement with the University, to become the first commercial tenant of the Energy Centre, researching gasification

£800k of variations to contract work undertaken yet the project was still delivered 4 weeks early – a 20% increase in project value

Local Labour
Target was 50% local labour – 88% within 10 miles was achieved
Local spend achieved was 85% within 40 miles

Training and Employment
15 local apprentices were employed on this project
4 education activities, 4 work placements and 3 community activities were undertaken

Environmental figures
290 tonnes of waste was removed from site
97.30% of waste was diverted from landfill

“We achieved completion 1 month ahead of schedule on what was already an extremely tight timescale. This project was highly challenging yet the team were extremely helpful, professional and highly effective at all times.” 

Richard Farrow, Head of Strategy, Performance and Impact, Thornton Science Park, University of Chester