Case Study

Bluelight

Lymm Response Hub and Safety Centre

Lymm, Cheshire

Client
Cheshire Fire and Rescue Service
Location
Lymm, Cheshire
Value
£7.2 Million
Contractor
ISG
Start
February 2016
Completion
March 2017
Sector
Bluelight
Form of Contract
JCT Design and Build
Delivery Type
Design and Construction

Construction of a new five-bay fire station in Lymm plus an advanced training facility and Safety Centre covering 13,500 sqm

• The contractor is utilising elements of BIM 3D design and clash detection to aid the overall design of this project

School Engagement and Student Development
• The contractor has established links with Mid Cheshire College and Warrington Collegiate, to offer site visits and work experience opportunities within its supply chain

Sustainability and Localism
• A Supply Chain Open Day was held in Cheshire supported by Mid Cheshire College and Cheshire West and Chester Council and attended by over 100 local suppliers
• The local Jobcentre Plus (JCP) has been engaged in order to create a “pathway into work” for local unemployed people and links have been forged with the Prince’s Trust to offer work placements
• Regular community briefings will be held to provide project updates to include question and answer sessions
• To promote the scheme, a groundbreaking event was organised with representatives of Cheshire Fire Authority and pupils from local schools

“This is an exciting development that will benefit this and future generations as we strive to achieve our vision of a Cheshire where there are no deaths, injuries or damage from fires and other emergencies. I am delighted, therefore that the Authority is able to invest in frontline response services.”
Cllr John Joyce, Chair of Cheshire Fire Authority