STEM Centre Laboratories Liverpool

Liverpool

Client
The City of Liverpool College
Location
Liverpool
Value
£2.1 Million
Contractor
ISG
Start
June 2016
Completion
September 2016
Sector
Education
Form of Contract
JCT Intermediate
Delivery Type
Construct Only

Refurbishment of the two-storey Clarence Street STEM facility to create modern laboratories and research space, covering an area of 1,600 sqm

Completion is critical for the start of the 2016/17 academic year, to provide students with brand new state-of-the-art facilities

• Clear logistics and delivery strategies will ensure minimal disruption and allow college activities to operate as normal
• Lean project management and construction techniques are being adopted to ensure the tight timescales are achieved
• Early 360 degree collaborative design workshops were held during the project’s pre-construction stage to avoid construction issues and programme delays

Sustainability and Localism
• The project has a target to achieve a BREEAM Very Good environmental rating
• Liverpool In Work have been engaged and work experience opportunities have been offered to their learners

College Engagement and Student Development
• The City of Liverpool College have been engaged, with curriculum support and work experience opportunities planned for their apprentices

“I am very pleased so far with both the commitment and professionalism of the ISG team. I am also encouraged at how well the project is progressing and I look forward to seeing the completed project.”
Allan Taylor, Technical Services Manager, The City of Liverpool College