Project Update – Crewe Market Hall refurbishment

Procured through our Low Value Framework by Cheshire East Council with work being completed by Framework Partner, F Parkinson, works are well underway on the refurbishment of Crewe Market Hall.

Internally, the new power-floated concrete slab has now been completed to the main area of the building whilst the shambles steel work has also been finished with works progressing to the historic timber.

High level painting has been undertaken ready for the mechanical and electrical first fix which has commenced.

Externally, the voussoir lights to Heath Street have been fitted, the scaffolding has been taken down to Hill Street and Heath Street and footings to the new toilet extension have been poured ready for brick and block-work.

Keep an eye out on our social channels and website for further updates on what is another interesting Hub project.