21.09.2017

Re-procurement Update: September 2017

Our existing High Value Framework expires on 26 August 2018, we anticipate having all re-procurement activities for its successor finalised by then.

Before that date we currently anticipate these indicative timescales:

Publishing the PQQ/RTP by the end of October 2017

Publishing the ITT by the end of February 2018

 

Our existing Medium Value Framework expires on 24 February 2019, we anticipate our early market engagement processes having been completed by Christmas 2017.

We currently anticipate these indicative timescales:

Publishing the PQQ/RTP – March 2018

Publishing the ITT – August 2018

 

Naturally, due to the timescales involved these dates may be subject to change, if that should happen we will keep the NWCH website updated.

Our existing Low Value Framework expires on 12 February 2020

© North West Construction Hub. Site by Drumbeat